Skip to content

Production run order

Summary

The production run order sequences parts to respect coupon gate dependencies and minimise the cost of failure. Four coupons are mandatory gates — if any fail, only that coupon needs reprinting before proceeding, not downstream production parts. The sequence also respects practical logistics: the longest PCCF prints run first to establish the dimensional baseline while other coupons are still printing.

Total print time: approximately 50 hours over 6–7 days for a complete single-drone production run.


Concept

Why order matters

Parts have dependencies: - X body PCCF layers cannot be produced until Coupon 8 (T-lock fit) passes. A failed PCCF layer wastes ~1.8 hours per layer (×3 = 5.5 hours total). - Platform cannot be produced until Coupons 10 and 11 pass. A failed Platform wastes ~3.5 hours. - Arm shafts should follow X body completion so the epoxy rod-sealing sequence can run continuously.

Running coupons first, then production parts in dependency order, reduces the maximum wasted print time in any failure scenario.


Reference

Production sequence

Step Part Qty Est. time Gate dependency
1 PETG Natural calibration coupons (1–3) ~1 h None
2 Coupon 8 — T-lock fit 1 tab + 1 X body section ~1 h GATE: must pass before step 3
3 X body PCCF layers 3 ~5.5 h total Coupon 8 pass
4 X body PETG top layer 1 ~1.5 h None (parallel with coupons)
Install heat-set inserts in mast boss pads ~15 min After step 4 print
5a Coupon 10 — GX12-7 chimney bore 1 block ~45 min GATE: must pass before step 5c
5b Coupon 11 — battery rail slide 1 section ~1 h GATE: must pass before step 5c
5c Platform 1 ~3.5 h Coupons 10 + 11 pass
Remove chimney bore supports; verify connector fit + battery slide on full Platform ~30 min After step 5c
6 Backplane lattice 1 ~1 h None
7 Arm tabs 8 ~2 h total None
Dry-fit all tabs into T-slots; verify T-lock before continuing ~15 min After step 7
8 Arm shafts — primary set 4 ~14 h total (3.5 h each) Coupon 8b pass
9 Arm shafts — spares 2 ~7 h total
10 Arm cover passive — PETG-CF 4 ~3 h total Coupon 6 pass (FFP3 respirator mandatory)
11 Arm cover active — PETG 4 ~2 h total Coupon 7 pass
12 ASA bumpers 8 + 4 spares ~1.5 h Coupon 4 pass
13 GPS/camera bracket 1 ~1 h Coupon 9 pass
14 Sensor mast + cradle 1 set ~1.5 h Coupon 5 pass

Post-production — mandatory steps before assembly

Step Action
Inspect all parts Check for layer delamination, stringing, under-extrusion
Weigh all parts Compare against mass targets in print-profiles
X body layers Epoxy wipe on rod channels (thin application, correct any gaps)
Arm shafts Epoxy rod channels at crossings — see airframe-integration
Platform Support removal from GX12 chimney bores; verify connector and battery tests
Arm tabs Dry-fit T-lock in all X body layer slots before epoxy

Coupon 8b gate — arm shafts

Before printing arm shaft production run: print Coupon 8b (rod interference fit in PETG). This is separate from the T-lock Coupon 8 because the interference fit tolerance is independent of the T-slot clearance.


Procedure

Managing parallel runs

Steps 3, 4, and 6 can overlap with the later coupon prints (5a, 5b) if you have one printer: - Run step 3 (PCCF layers) on days 1–2 if printer is available overnight. - Run step 4 (PETG top) as a daytime print while you review PCCF results. - Run coupons 10 and 11 before starting Platform — not before X body.

If you have two printers: PCCF layers and arm coupons can run in parallel.

Epoxy log

Record every epoxy application: - Date and time - Part and location - Mass before and after (epoxy delta) - Maximum permitted deltas: shaft 1.0 g, tab 0.5 g, X body layer 1.5 g, full frame total 8.0 g


Rationale

Why arm shafts are step 8 rather than step 2

Arm shafts are long vertical prints requiring 3.5 hours each with no opportunity for early failure detection. If the T-lock coupon (step 2) reveals a variable adjustment that also affects rod channel geometry, arm shaft reprinting may be required. Starting shafts after the X body dimensional baseline is confirmed avoids this risk.

Why PCCF layers are step 3 rather than later

PCCF layers are the longest single batch print in the sequence. Starting them as early as possible (after Coupon 8 passes) keeps the critical path short. If a PCCF layer fails mid-print, there is time to diagnose and reprint within the production window without extending the overall schedule.


Connections

requires: - coupon-validation - print-profiles related: - stl-export-and-slicer-setup - airframe-integration leads_to: - stl-export-and-slicer-setup - airframe-integration